Georgia Roof Guide

Where does drip edge go, and how is it placed?

Short answer. Drip edge goes along every eave and every rake of the roof. At the eaves it is installed directly on the deck under the underlayment, and along the rakes it goes on top of the underlayment, so water at each edge always runs over the metal and away from the wood.

At the eaves

Along the rakes

Fastening and laps

Nails go high on the roof flange, where shingles will cover them, no more than 12 inches apart. Joints overlap at least 2 inches, with the upper or downstream piece lapped correctly so water runs over the seam. At outside corners, the rake piece laps over the eave piece.

Where drip edge does not go

Hips, ridges and valleys are interior lines covered by caps and valley linings. Where a roof meets a wall, step flashing and headwall flashing do the job instead. Low-slope porch roofs with membrane roofing use their own edge metal.

A common placement mistake

Setting eave drip edge on top of the underlayment lets water running down the sheet slip behind the metal and onto the fascia, the very thing drip edge is meant to prevent.

See drip edge explained and gutter sizing and guards.

In depth

What are the types of roof flashing, and should old flashing be reused?Step, counter, apron, valley and kickout flashing explained for Georgia homes, what the code requires, and whyArchitectural or 3-tab shingles: which is right for a Georgia home?Architectural vs 3-tab shingles in Georgia: weight, wind warranties, lifespan, availability as 3-tab lines shrWhat shingle color is best for a hot Georgia summer?How shingle color changes roof and attic heat in Georgia, what cool roof shingles really reflect, where to fin

People also ask