Should you replace the roof and siding at the same time?

Short answer. Doing both together can make sense, especially after a hailstorm that damaged both, but the roof should go first or the two crews must coordinate the roof-to-wall flashing. Step flashing, kickout flashing and the trim where roof meets wall are shared details that leak when neither trade owns them.

Order of work

  1. Roof first. Tear-off drops debris down the walls, and the roofer installs step flashing and kickout flashing against the wall sheathing.
  2. Siding second. The siding crew installs house wrap and siding over the vertical legs of the step flashing, so water stays on the outside of every layer.
  3. Gutters last, once fascia and trim are finished.

If the siding goes on first, the roofer either has to cut into new siding to replace flashing or reuse old flashing behind it, which is a common source of leaks.

The details where they meet

After a storm

Hail that bruises shingles often cracks vinyl siding, dents aluminum and chips paint. Document everything at once, because the claim covers the whole house, not just the roof. Coverage depends on your policy, and matching on siding is its own conversation with the adjuster.

Who does what

Get each contractor's scope in writing, including who supplies and installs the kickout flashing, and schedule the siding crew to start after the roof passes its final check. Read roof flashing explained and common roof leak causes for why wall joints fail.

In depth

What happens on roof replacement day?What really happens when a Georgia roof is replaced: prep, tear-off, deck repairs, flashing, nailing, crew safCan you put new shingles over old ones in Georgia?Georgia's code allows one shingle layover in limited cases, never over two layers. Learn the rules, manufacturShould you replace your roof before installing solar panels?Solar panels outlast many Georgia shingle roofs. How to weigh roof age against panel life, reinstall costs, wa

People also ask